Design calculations for form work of PIER

I have learn about the form work of PIER.  Form work is the term given to either temporary or permanent molds into which concrete or similar materials are poured.

I have make spreadsheet with help of Dr. Harvinder Singh and Dr. H.S RAI . The calculations for form work of pier is done by reading IS code 14687 and IS code 875 (Part-3). To understand the calculations is little difficult for me but finally i completed my work on time. It is easy to make spreadsheet by putting formulae and also i learnt more commands which make easy to make spreadsheet. To know more about the form work then click to;  https://www.google.co.in/search?q=formwork&oq=formwork&aqs=chrome..69i57j0l5.6269j0j7&sourceid=chrome&es_sm=93&ie=UTF-8

Leave a comment